Complete the following MPS Record (calculate net requirements as well as ATP): On hand=30, Lot size=40, Lead time=1, Safety stock=8 Period0 1 2345678 Forecast2020202015151515 Orders
Complete the following MPS Record (calculate net requirements as well as ATP):
On hand=30, Lot size=40, Lead time=1, Safety stock=8
Period0 1 2345678
Forecast2020202015151515
Orders booked2010208
Scheduled receipt
Projected on hand
(Period end)
MPS quantity
MPS start
Net requirement ______________________________________________________________________________
Available-to-promise (ATP)