Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete
Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). 1 2 3 4 5 6 Week ***A2*** LT(weeks) = 3 100 0 400 400 500 250 40 Gross requirements Scheduled receipts Projected ending inventory: 300 Net requirements Planned receipts Min. order = 1 Planned orders