Complete the following MRP record. Lead time for the part is 2 weeks. The lot size is 1000. On-hand inventory is 1000. What is the
Complete the following MRP record. Lead time for the part is 2 weeks. The lot size is 1000. On-hand inventory is 1000.
What is the projected available inventory at the end of week 3?
In which period is it planned to release an order?
Week | 1 | 2 | 3 | 4 |
Gross Requirements | 250 | 750 | 1000 | 1000 |
Scheduled Receipts | 1000 | |||
Projected On-hand Inventory | ||||
Planned Receipt | ||||
Planned Order Release |
Complete the following MRP record. Lead time for the part is 2 weeks. The lot size is 1000 . On-hand inventory is 1000. What is the projected available inventory at the end of week 3 ? In which period is it planned to release an order
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started