Complete the MRP planning schedules given the BOM and Demand for Component. (10 pts) A B(2) Component A Lead Time = 1 period, Safety Stock
Complete the MRP planning schedules given the BOM and Demand for Component. (10 pts)
A
B(2)
Component A Lead Time = 1 period, Safety Stock = 0, Fixed order size = 50
Period | BI | 1 | 2 | 3 | 4 | 5 |
Demand (gross requirements) | 100 | 150 | 150 | 100 | 175 | |
Schedule Receipt | 200 | |||||
Projected Inventory | 0 | 100 | -50 | -200 | -300 | -425 |
Net Requirement | 0 | 50 | 150 | 100 | 175 | |
Planned Order Receipt | 50 | 150 | 100 | 200 | ||
Planned Order Release | 50 | 150 | 100 |
Component B Lead Time = 1 period, Safety Stock = 0, fixed order size = lot-for-lot
Period | BI | 1 | 2 | 3 | 4 | 5 |
Demand (gross requirements) | 200 | 300 | 300 | 200 | 350 | |
Schedule Receipt | 175 | |||||
Projected Inventory | 25 | -25 | -325 | -625 | -825 | -1175 |
Net Requirement | 25 | 300 | 300 | 200 | 350 | |
Planned Order Receipt | 25 | 300 | 300 | 200 | 350 | |
Planned Order Release | 25 | 300 | 300 | 300 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started