Complete the MRP planning schedules given the BOM and Demand for Component. (10 pts) A B(2) Component A Lead Time = 1 period, Safety Stock

Complete the MRP planning schedules given the BOM and Demand for Component. (10 pts)

A

B(2)

Component A Lead Time = 1 period, Safety Stock = 0, Fixed order size = 50

Period BI 1 2 3 4 5
Demand (gross requirements) 100 150 150 100 175
Schedule Receipt 200
Projected Inventory 0 100 -50 -200 -300 -425
Net Requirement 0 50 150 100 175
Planned Order Receipt 50 150 100 200
Planned Order Release 50 150 100

Component B Lead Time = 1 period, Safety Stock = 0, fixed order size = lot-for-lot

Period BI 1 2 3 4 5
Demand (gross requirements) 200 300 300 200 350
Schedule Receipt 175
Projected Inventory 25 -25 -325 -625 -825 -1175
Net Requirement 25 300 300 200 350
Planned Order Receipt 25 300 300 200 350
Planned Order Release 25 300 300 300

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Operations and Supply Chain Management

Authors: Cecil B. Bozarth, Robert B. Handfield

3rd edition

132747324, 978-0132747325

More Books

Students also viewed these General Management questions