____ completes a review of the OPR, BOD, and design documents to verify that the program's goals are properly included in the design documents. Group
____ completes a review of the OPR, BOD, and design documents to verify that the program's goals are properly included in the design documents. Group of answer choices Owner Design team member Construction team member Subcontractor of construction team member Commissioning authority