Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes:
Compute Lead Time
Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 2 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.
Traditional Philosophy | Lean Manufacturing Philosophy | |||
Value-added time | fill in the blank 1 | min | fill in the blank 2 | min |
Non-value-added time | fill in the blank 3 | min | fill in the blank 4 | min |
Total lead time | fill in the blank 5 | min | fill in the blank 6 | min |
Value-added ratio (as a percent) | fill in the blank 7 | % | fill in the blank 8 | % |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started