Compute the following variances from the data given below : (a) Total sales margin variance (b) Sales margin volume variance (c) Sales margin price variance
Compute the following variances from the data given below :
(a) Total sales margin variance
(b) Sales margin volume variance
(c) Sales margin price variance
(d) Sales margin quantity variance
(e) Sales margin mix variance.
Product Budgeted quantity (units) A B 240 160 Actual quantity (units) 400 200 Budgeted sale price per unit (Rs.) 50 25 Actual sale price per unit (Rs.) 45 20 Standard cost per unit (Rs.) 30 15
Step by Step Solution
★★★★★
3.41 Rating (145 Votes )
There are 3 Steps involved in it
Step: 1
For Product A Budgeted Quantity units 240 Actual Quantity units 400 Budgeted Sales Price per Unit Rs 45 Standard Cost per Unit Rs 30 Actual Sales Pric...Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started