Compute the Labor Variance with work shown from the table below Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate:

Compute the Labor Variance with work shown from the table below

Actual Material used: 30,000 Actual Cost: $7.75/Unit Actual Labor Hrs: 33,000 Actual Labor Rate: $15/Hr:

Budgeted production (units) 16,600 20,600 22,800 60,000
Labor requirements per unit (hours) 0.5 0.5 0.5 0.5
Total labor hours needed 8,300 10,300 11,400 30,000
Labor rate (per hour) $16 $16 $16 $16
Labor dollars $132,800 $164,800 $182,400 $480,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Ebook Principles Of Financial Accounting

Authors: John Wild, Ken Shaw, Barbara Chiappetta

2nd Edition

0077166183, 9780077166182

More Books

Students also viewed these Accounting questions