Question
1 Approved Answer
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your finalanswer to 2 decimal places.)
Project MTime:0 1 2 34 5
Cash flow:-$3,500 $750 $880 $920 $1,000 $500
What is the NPV?
Should the project be accepted or rejected?