Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is
Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.
Time: | 0 | 1 | 2 | 3 | 4 | 5 |
---|---|---|---|---|---|---|
Cash flow: | 100 | 100 | 0 | 150 | 125 | 100 |
Multiple Choice
a. $62.96
b. $69.26
c. $112.04
d. $260.17