Compute the number of kanbans (trays) necessary for this process. Average leadtime =4.0 hours Average demand during leadtime =95 parts per hour Safety stock required
Compute the number of kanbans (trays) necessary for this process. Average leadtime =4.0 hours Average demand during leadtime =95 parts per hour Safety stock required = J. Each tray or kanban holds 80