compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the desired service level is 98% (which corresponds to z-2.06,
compute the reorder point when weekly demand is 100 units, lead time is 2 weeks, the desired service level is 98% (which corresponds to z-2.06, standard deviations from the mean) and the standard deviation of demand during lead time is 30 units.