CON325 Construction Company Financial Management Spring 2023 HW 3 Earned Value Method Due: Tuesday 2/14/23 Read the information carefully and answer the questions given. Show all your work for full credit. After three months on the job (July 1), the contractor concluded that 20% of Activity F (Activities A, B, and Dare completed) was completed, 80% of Activity C was completed, and 40% of Activity E was completed. The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the Schedule Variance (SV), the Cost Variance (CV), Percent Completion (PC), and Estimated Cost at Completion (EAC). State if the project is over or under budget and if it is ahead or behind schedule. Grade Rubric: 1. Completion of setting up equations and calculation for SV, CV, PC, and EAC (20 points each). 2. Correct answer for each value ( 5 points each). CON325 Construction Company Financial Management Spring 2023 HW 3 Earned Value Method Due: Tuesday 2/14/23 Read the information carefully and answer the questions given. Show all your work for full credit. After three months on the job (July 1), the contractor concluded that 20% of Activity F (Activities A, B, and Dare completed) was completed, 80% of Activity C was completed, and 40% of Activity E was completed. The project has cost the contractor a total of $535. For this project, using earned value concepts, determine the Schedule Variance (SV), the Cost Variance (CV), Percent Completion (PC), and Estimated Cost at Completion (EAC). State if the project is over or under budget and if it is ahead or behind schedule. Grade Rubric: 1. Completion of setting up equations and calculation for SV, CV, PC, and EAC (20 points each). 2. Correct answer for each value ( 5 points each)