Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A - 2
Conider the project schedule shown in the table below. Times are given in days.
Activity | Predecessor(s) | Duration | ES | EF | LS | LF | Slack |
A | - | 2 | 0 | 2 | 0 | 2 | 0 |
B | A | 7 | 7 | ||||
C | A | 4 | 2 | 6 | |||
D | B | 2 | 7 | 9 | 17 | 10 | |
E | B, C | 4 | 7 | 11 | 7 | 11 | 0 |
F | C | 5 | 6 | 11 | 0 | ||
G | E, F | 8 | 11 | 19 | 11 | 0 |
What is the LS time for activity B?
The LS time for activity B is
enter your response here
days.
What is the project duration?
The project duration is
enter your response here
days.
What are the critical
activities?
(Enter your answer as a sequence of capital letters with no dashes or spaces.)
The critical activities are
enter your response here.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started