Conider the project schedule shown in the table below. Times are given in days. Activity Predecessor(s) Duration ES EF LS LF Slack A - 2

Conider the project schedule shown in the table below. Times are given in days.

Activity Predecessor(s) Duration ES EF LS LF Slack
A - 2 0 2 0 2 0
B A 7 7
C A 4 2 6
D B 2 7 9 17 10
E B, C 4 7 11 7 11 0
F C 5 6 11 0
G E, F 8 11 19 11 0

What is the LS time for activity B?

The LS time for activity B is

enter your response here

days.

What is the project duration?

The project duration is

enter your response here

days.

What are the critical

activities?

(Enter your answer as a sequence of capital letters with no dashes or spaces.)

The critical activities are

enter your response here.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L. Daft, Dorothy Marcic

11th Edition

0357033825, 9780357033821

More Books

Students also viewed these General Management questions