Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for
Consider a capital budgeting example with five projects from which to select. Let xi = 1 if project i is selected, 0 if not, for i = 1,...,5.
Write the appropriate constraint(s) for each condition. Conditions are independent.
a. Projects cost 200, 400, 250, 75, and 300 respectively. The budget is 1100. b. Choose no more than three projects. c. If project 3 is chosen, project 2 must not be chosen. d. If project 2 is chosen, project 4 must be chosen. e. No fewer than two of projects 1, 2, and 3 must be chosen.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started