Question

1 Approved Answer

Consider a job shop currently dedicated to two one-time customer orders. Job 1 takes 5 days to process and job 2 takes 8 days. The

Consider a job shop currently dedicated to two one-time customer orders. Job 1 takes 5 days to process and job 2 takes 8 days. The company paid the materials for both jobs 2 day after the start of processing. The customer for job 1 pays the immediately upon the completion of the job, while customer for job 2 pays 1 day before the completion of the job. The cost and revenue for the jobs are listed below.

Job 1 Job 2
Processing time 5 8
Time to pay 2 2
Amount to pay $2 $5
Time to receive 0 -1
Amount to receive $4 $8

When job 1 is processed before job 2, the cash gradient is:

Below 0.5

0.51 0.60

0.61 0.70

0.71 0.80

0.81 0.90

0.91 1.00

1.01 1.10

1.11 1.20

1.21 1.30

Above 1.3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions