Consider a process consisting of three resources. Assume there exists unlimited demand for the product, and that all activities are always performed in the following sequence. - Resource 1 has a processing time of 7 minutes per unit. - Resource 2 has a processing time of 4 minutes per unit. - Resource 3 has a processing time of 6 minutes per unit. All three resources are staffed by one worker and each worker gets paid $14 per hour. Do not round your intermediate calculations. Round your answer to 2 decimal places. a. What is the cost of direct labor? per unit Do not round your intermediate calculations. Round your answer to nearest whole number. b. What is the labor content? Do not round your intermed ate calculations. Round your answer to 2 decimal places. c. What is the average labor utilization? percent Do not round your intermediate calculations. Round your answer to 2 decimal places. d. Assume the demand rate is 15 units per hour. What is the takt time? minutes per unit Do not round your intermediate calculations. Round your answer to 2 decimal places. e. Assume the demand rate is 15 units per hour, What is the target manpower? employoes Do not round your intermediate calculations. Round your answer to 1 decimal place. f. If one addational worker could be hired, to which resource shoold the additional resources be assigned? Calculate the process capacity. units per hour. Do not round your intermediate calculations. Round your answer to 1 decimal place. b. What is the labor content? minutes per unit Do not round your intermediate calculations. Round your answer to 2 decimal places. c. What is the average labor utilization? percent Do not round your intermediate calculations. Round your answer to 2 decimal places. d. Assume the demand rate is 15 units per hour. What is the takt time? minutes per unit Do not round your intermediate calculations. Round your answer to 2 decimal places. 0. Assume the demand rate is 15 units per hour. What is the target manpower? Do not round your intermedlate calculations. Round your answer to 1 decimal place. f. If one additional worker could be hired, to which resource should the addisional resources be assigned? Calculate the process capacity. units per hour Do not round your intermediate calculations. Round your answer to 1 decimal place. 9. If they could take 1 minute of tank time from one resource and give it to another resource (so the labor content remains the same). What would be the new capacity of the process (units per hour)? Assume that there is ssill only 1 worker per station. units per hour Do not round your intermediate calculations. Round your answer to 1 decimal place. What would be the capacity of the process if they integrated the work so that all workers h. do all three tasks (units per hour)? Assume that there is still only 1 worker per station