Consider a process consisting of three resources; each resource is staffed by two workers. Resource #1 has a processing time of 10 minutes per unit.
Consider a process consisting of three resources; each resource is staffed by two workers.
Resource #1 has a processing time of 10 minutes per unit.
Resource #2 has a processing time of 8 minutes per unit.
Resource #3 has a processing time of 4 minutes per unit.
Assume each worker gets paid $15 per hour. Each unit is sold for $6 and includes parts that are sourced for $1 which is the variable cost. The company has fixed costs of $10 per hour. Demand rate is assumed as 13 units per hour.
What is the idea cycle time to meet the demand? (25/100)
Which option is the best in terms of the profit per hour? (Calculate the profit of each option to choose the best one.)
Option #1: 10% lower material costs (25/100)
Option #2: 10% lower fixed costs (25/100)
Option #3: 10% faster at bottleneck (25/100)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started