Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A C, E 4 2 $2000
Consider a project having the following six activities:
Immediate Max Crash cost
Activity Predecessors Time (weeks) Crash* per week
A C, E 4 2 $2000
B A 6 2 $1000
C none 6 6 N/A
D C 3 2 $1000
E none 5 2 $500
F A, D 5 2 $1250
*Shortest possible time for the task
- Draw the project network.
- List the earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) for each task.
- List all potential paths and duration.
- List all the tasks on the critical path.
- What is the expected project duration in weeks?
- What is the slack for each activity? A: B: C:____ D: E: F:
- The project needs to be crashed by 2 weeks. What activity or activities should be crashed to achieve the 2 week needed and what is the cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started