Question

1 Approved Answer

Consider a project that consists of 8 tasks with predecessors and task estimates as shown: Task Predecessor Min. Most Likely Max. Expected Time Variance A

Consider a project that consists of 8 tasks with predecessors and task estimates as shown:

Task

Predecessor

Min.

Most Likely

Max.

Expected Time

Variance

A

-

1

2

6

2.5

0.7

B

A

4

7

8

6.7

0.4

C

A

3

4

5

4.0

0.1

D

B, C

7

8

12

8.5

0.7

E

D

4

8

9

7.5

0.7

F

D

3

6

9

6.0

1.0

G

D

2

3

5

3.2

0.3

H

G

5

6

8

6.2

0.3

Using "expected times" for each task, what is the critical path?

options:

A, B, C, D, E

A, B, D, E, H

A, B, D, G, H

A, C, D, G, H

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quality Management In Construction Projects

Authors: Abdul Razzak Rumane

2nd Edition

0367890038, 978-0367890032

More Books

Students also viewed these General Management questions