Consider a project with the following paths:
A-B-C-D-H (21 days)
A-B-E-G-H (20 days)
A-J-K-L (20 days)
A-J-K-M (18 days)
Which of the following would successfully shorten the project by two days. (Choose all that apply).
a.
Crash B by one day and H by one day
b.
Crash M by three days
c.
Crash J by one day and B by one day
d.
Crash C by two days and B by one day
e.
Crash D by one day, H by one day, G by one day
f.
Crash B by two days
g.
Crash H by 2 days and K by 1 day
h.
Crash C by one day, B by one day, L by one day
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started