Question

1 Approved Answer

Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items

Consider a single activity process with 1 worker. The activity time is 4 minutes per unit. The defect rate is 40% and the defective items are routed to a sperate rework station with 2 workers. The rework time is 16 minutes per unit. The process capacity is within


Question 1 options:



Below 8 units per hour



8.1 - 16 units per hour



16.1 – 20 units per hour



20.1 – 24 units per hour



Above 24.1 units per hour

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

Step: 1

81 16 units per hour Explanation 1 worker working for 4 minutes produces 1 unit Therefore ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Materials Management

Authors: Arnold J. R. Tony, Gatewood Ann K., M. Clive Lloyd N. Chapman Stephen

8th edition

9386873249, 134156323, 978-9386873248

More Books

Students also viewed these Human Resource Management questions