Question

1 Approved Answer

Consider a software project with 5 tasks T1-T5. Duration of the 5 tasks (in days) are 15, 10, 12, 25 and 10, respectively. T2 and

Consider a software project with 5 tasks T1-T5. Duration of the 5 tasks (in days) are 15, 10, 12, 25 and 10, respectively. T2 and T4 can start when T1 is complete. T3 can start when T2 is complete. T5 can start when both T3 and T4 are complete.

i) Draw the Gantt Chart and PERT charts for the project.

ii) When is the latest start date of the task T3? What is the slack time of the task T4? What is the slack time of the task T2?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Database Fundamentals Study Guide

Authors: Dr. Sergio Pisano

1st Edition

B09K1WW84J, 979-8985115307

More Books

Students also viewed these Databases questions