Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 5, 25, 35. Estimate the standard deviation of the activity time. (Standard
Consider an activity with these estimates for optimistic, most likely, and pessimistic time: 5, 25, 35. Estimate the standard deviation of the activity time. (Standard deviation, not the variance)
( Please provide answer accurate to two decimal places )