Consider projects A and B with the following cash flows: C0 C1 C2 C3 A $ 39 + $ 23 + $ 23 + $
Consider projects A and B with the following cash flows:
C0 C1 C2 C3
A $ 39 + $ 23 + $ 23 + $ 23
B 64 + 33 + 33 + 33
1). What is the NPV of each project if the discount rate is 15%? (Do not round intermediate calculations. Round your answers to 2 decimal places.)
Project A: NPV: ????
Project B: NPV: ????
2). What is the profitability index of each project? (Do not round intermediate calculations. Round your answers to 2 decimal places.)
Project A: Profitability Index: ???
Project B: Profitability index: ???
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started