Question

1 Approved Answer

Consider that we have the following three time estimates for each of the tasks. Tasks Optimistic time (to) Pessimistic time (to) Expected duration (te) Most

image text in transcribed
Consider that we have the following three time estimates for each of the tasks. Tasks Optimistic time (to) Pessimistic time (to) Expected duration (te) Most likely time (tm) 2 5 3 A 1 3 B 3 1 D 5 5 2 E 7 5 13 9 6 6 7 4 F a. Determine the expected duration of each task as well as the total estimate for the project. Include both the total estimate for the project as well as the standard deviation for the total path. Show all work. (11 marks) b. If everything went better than expected what would be the earliest possible time for the project to be completed (earliest completion date) along with the standard deviation. Show all paths (5 marks) If everything went worse than expected what would be the latest possible time for the project to be completed (latest completion date) along with the standard deviation. Show all paths (5 marks) C

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Chemical Engineering Design

Authors: Ray Sinnott, R.K. Sinnott, Sinnott Gavin Towler

6th Edition

0081025998, 9780081025994

More Books

Students also viewed these Chemical Engineering questions

Question

c. Greater union activity leads to higher nominal wages.

Answered: 1 week ago

Question

I Which of your reasons (if any) were not under your controli>

Answered: 1 week ago