Consider the activities, durations, and predecessor relationships in the following network. Draw the Network Diagram. Activity Description Immediate Predecessor ( s ) Optimistic ( Weeks

Consider the activities, durations, and predecessor relationships in the following network. Draw the Network Diagram.
Activity Description
Immediate
Predecessor(s)
Optimistic
(Weeks)
Most Likely
(Weeks)
Pessimistic
(Weeks)
A
---
4
7
10
B
A
2
8
20
C
A
8
12
16
D
B
1
2
3
E
D, C
6
8
22
F
C
2
3
4
G
F
2
2
2
H
F
6
8
10
I
E, G, H
4
8
12
J
I
1
2
3
a. What is the expected time for activity B?
b. What is the variance for activity B?
c. Based on the calculation of estimated times, what is the critical path?
d. What is the estimated time of the critical path?
e. What is the activity variance along the critical path?
f. What is the probability of completion of the project before week 42?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Methods For Business

Authors: David Anderson, Dennis Sweeney, Thomas Williams, Jeffrey Cam

11th Edition

978-0324651812, 324651813, 978-0324651751

More Books

Students also viewed these General Management questions

Question

Distinguish a flexible exchange rate from a fixed exchange rate.

Answered: 1 week ago

Question

2. Explica que relacin guarda la planeacin estratgica con una fusin

Answered: 1 week ago