Consider the activities, durations, and predecessor relationships in the following network. Draw the Network Diagram. Activity Description Immediate Predecessor ( s ) Optimistic ( Weeks
Consider the activities, durations, and predecessor relationships in the following network. Draw the Network Diagram.
Activity Description
Immediate
Predecessors
Optimistic
Weeks
Most Likely
Weeks
Pessimistic
Weeks
A
B
A
C
A
D
B
E
D C
F
C
G
F
H
F
I
E G H
J
I
a What is the expected time for activity B
b What is the variance for activity B
c Based on the calculation of estimated times, what is the critical path?
d What is the estimated time of the critical path?
e What is the activity variance along the critical path?
f What is the probability of completion of the project before week
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started