Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity Description Immediate Predecessor(s) Optimistic

Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow.

Activity Description

Immediate Predecessor(s)

Optimistic (Weeks)

Most Likely (Weeks)

Pessimistic (Weeks)

A

---

4

7

10

B

A

2

8

20

C

A

8

12

16

D

B

1

2

3

E

D, C

6

8

22

F

C

2

3

4

G

F

2

2

2

H

F

6

8

10

I

E, G, H

4

8

12

J

I

1

2

3

a) Draw the precedence diagram. (5 points)

b) What is the critical path? (5 points)

c) What is the probability of completion of the project after week 42?


Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Paul Griffin

2nd Canadian edition

978-0133764345

More Books

Students also viewed these General Management questions

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago

Question

What is the expected value with perfect information?

Answered: 1 week ago