Consider the AON graph of a project shown below. The activity times are 2 , 5 , 1 , 4 , 9 , 2 ,

Consider the AON graph of a project shown below.
The activity times are 2,5,1,4,9,2,3, and 4 days for activities A1 through A8, respectively.
What is the earliest completion time of the project?
Project time
days
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurial Small Business

Authors: Jerome Katz, Richard Green

4th edition

78029422, 978-0077513009, 77513002, 978-0078029424

More Books

Students also viewed these General Management questions