Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and
Consider the following activity-on-arc project network, where the 12 arcs (arrows) represent the 12 activities (tasks) that must be performed to complete the project and the network displays the order in which the activities need to be performed. The number next to each arc (arrow) is the time required for the corresponding activity. Consider the problem of finding the longest path (the largest total time) through this network from start (node 1) to finish (node 9), since the longest path is the critical path.
(a) Formulate the network flow model for the corresponding diagram.
(b) What is the logical resoning behind the fact that the longest path in a network is chosen to be the critical path.
Figure 1Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started