Question

1 Approved Answer

Use this information to answer the following questions. Consider the following Activity-On-Node (AON)PERT project.The three values that represent each activity's completion time (in days)correspond

 

Use this information to answer the following questions. Consider the following Activity-On-Node (AON)PERT project.The three values that represent each activity's completion time (in days)correspond to an optimistic time,most likely time.and pessimistic time,respectively. 4-5-6 2-3-4 D 4-5-6 3-4-5 F A 5-6-7 3-4-5 E -Refer to the figure.What is the probability of completing the project within 18 days? A)0)0668 B)0)4332 C)0)9332 D)0)4878 E)0)0122

Step by Step Solution

3.48 Rating (158 Votes )

There are 3 Steps involved in it

Step: 1

ANSWER 1 00668 EXPLANATION EXPECTED TIME A 4M B 6 WHERE A OPTIMISTIC TIME M MOST LIKELY TIME B PESSI... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management

Authors: Harvey maylor

4th Edition

027370432X, 978-0273704324

More Books

Students also viewed these Accounting questions

Question

Determine A in the indicated figures. Fig. 2.40 (a) A 84 (a) 40 B

Answered: 1 week ago

Question

ii. Tenacity Study?

Answered: 1 week ago