Consider the following construction project's time phased budget plan. Activity January February March April Survey 8,000 Design 5,250 Dirt Foundation Framing Plumb Wire What is
Consider the following construction project's time phased budget plan. Activity January February March April Survey 8,000 Design 5,250 Dirt Foundation Framing Plumb Wire What is the cumulative cost in February? Select one: OA. $50,550 B. $37,000 C. $87,550 D. $45,050 E. $23,750 acBook Air & 7 F7 U * 8 DII F8 4,500 6,700 12,550 | ( 9 37,250 7,800 A F9 0 ) 0 5,500 F10 P F11 { [ + 11 20:12 F12 } ] G 0 delete 1