Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Consider the following data for the project newt work that corresponds to the warehouse expansion case problem. Activity Optimistic Most Probable Pessimistic Imm. Predecessor A
Consider the following data for the project newt work that corresponds to the warehouse expansion case problem.
Activity
Optimistic
Most Probable
Pessimistic
Imm. Predecessor
A
B
C
A B
D
C
E
C
F
E
G
C
H
D F G
I
D F
J
H
K
I, J
Answer the following questions taking into consideration the additional information provided.
a Develop the project newt work with activity scheduling ie a table defining start time and finish time of each activity as well as the slack and the critical path What is the expected project completion time? What is its corresponding variance? Marks
b Determine the probability that the project can be completed in weeks and weeks? Marks
c Using the expected activity times as the normal time and the following crashing activity information provided below. Determine the activity crashing decisions activities # of crashing day per activity, cost of crashing per crashed activity and the total cost in order to reduce the expected project completion time by weeks ie weeks less than the expected project completion time obtained in part a
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started