Question
1 Approved Answer
Consider the following information of a project: Activity Predecessor A B D E Normal time Crash time Crash Cost (weeks) (weeks) per week 6 5
Consider the following information of a project: Activity Predecessor A B D E Normal time Crash time Crash Cost (weeks) (weeks) per week 6 5 80 12 6 110 4 3 100 5 3 210 8 5 140 A Calculate the minimum cost of crashing by 1 week. Your
Step by Step Solution
There are 3 Steps involved in it
Step: 1