Consider the following jobs that start and finish at the following times: Start 5 3 1 7 6 1 9 Finish 8 8 4 12
Consider the following jobs that start and finish at the following times:
Start 5 3 1 7 6 1 9
Finish 8 8 4 12 10 3 15
Show which jobs the activity-selection algorithm would choose. Show all work.