Consider the following layout of a car washing process: Scrubbing (4 minutes) -------> Rinsing (8 minutes) --------> Drying (4 minutes) What is the cycle time
Consider the following layout of acar washingprocess:
Scrubbing (4 minutes) -------> Rinsing (8 minutes) --------> Drying (4 minutes)
What is thecycle timeof the line?