Question: Consider the following periodic task-set Task Period Deadline Execution Time 1 3 3. 1 8 8. 4 9. 9. 1 Determine the feasible cyclic

Consider the following periodic task-set Task Period Deadline Execution Time 1 3 3. 1 8 8. 4 9. 9. 1 Determine the feasible cyclic executive schedule by answering the following sub-questions. Provide proper explanation for your answers: 1. (2) Test if the given task-set is schedulable under RM, using the sufficient test 2. (8) Test if the given task-set is schedulable under RM, using the necessary test. 3. (5) Assume that the first job of each task arrives at time 0. Construct the schedule for the interval [0, 20] and illustrate it graphically. In case they exist, identify deadline misses. 4. (3) Determine the maximum utilization which is always scheduleable using RM scheduling, using the sufficient schedulability test.