Consider the following process flow chart, with resources and processing times given below each activity. machine a - 3 min / units; machine b 4
Consider the following process flow chart, with resources and processing times given below each activity.
machine a minunits; machine b min unit ; machine minunit
a What is the flow time?
b What is the process capacity?
c What is the utilization of Activity
d Which Activity is the bottleneck