Question
Consider the following process Resource Resource Processing Time (Min./Unit) Number of workers 1 10 2 2 6 1 3 16 3 Question 1 (1 point)
Consider the following process Resource
Resource | Processing Time (Min./Unit) | Number of workers |
1 | 10 | 2 |
2 | 6 | 1 |
3 | 16 | 3 |
Question 1 (1 point) Saved What is the bottleneck? Question 1 options: Resource 1 Resource 2 Resource 3 Resource 2 and 3 Question 2 (1 point) Saved Question 2 options: The process capacity is ------------ units per hour [please use numerals to fill in the blank] Question 3 (1 point) Saved If demand is twelve units per hour, the utilization of each resource is Question 3 options: Resource 1: 30%, Resource 2: 100%, Resource 3: 12.5% Resource 1: 100%, Resource 2: 120%, Resource 3: 106.6% Resource 1: 60%, Resource 2: 200%, Resource 3: 25% Resource 1: 83.3%, Resource 2: 100%, Resource 3: 88.9% Question 4 (1 point) If demand is twelve units per hour, the implied utilization of each resource is Question 4 options: Resource 1: 30%, Resource 2: 100%, Resource 3: 12.5% Resource 1: 60%, Resource 2: 200%, Resource 3: 25% Resource 1: 100%, Resource 2: 120%, Resource 3: 106.6% Resource 1: 83.3%, Resource 2: 100%, Resource 3: 88.9%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started