PID | Arrival time | Burst Time | Priority |
---|---|---|---|
1 | 0 | 6 | 5 |
2 | 2 | 10 | 3 |
3 | 6 | 6 | 2 |
4 | 8 | 4 | 4 |
If Shortest Remaining Time First Scheduling (Shortest Job First) with preemption is used, what is the average waiting time for the 4 processes ?