Consider the following project data: Total Budget: $1,200,000 Actual Costs to Date: $650,000 Planned Value (PV) to Date: $700,000 Earned Value (EV) to Date: $600,000
Consider the following project data:
- Total Budget: $1,200,000
- Actual Costs to Date: $650,000
- Planned Value (PV) to Date: $700,000
- Earned Value (EV) to Date: $600,000
Questions:
- Calculate the Cost Performance Index (CPI).
- Calculate the Schedule Performance Index (SPI).
- Discuss the implications of the CPI and SPI values for the project.