Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the following project network and cost/time information. This project has a $80/day indirect cost: Activity Precedence Normal Time Crash Time Normal Cost Crash Cost

Consider the following project network and cost/time information. This project has a $80/day indirect cost:

Activity Precedence Normal Time Crash Time Normal Cost Crash Cost
A - 5 4 50 70
B A 4 2 70 80
C A 5 2 50 140
D B 1 Can't be crashed 90 -
E C 2 1 50 60
F D, E 3 1 200 600
  • What is the direct cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
  • What is the total cost of completing this project using the normal times? (Enter a numerical value without "$" or ",")
  • If you were asked to reduce the project completion time by one time unit, which activity would you crash?
  • What is the indirect cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")
  • What is the total cost of this project if we reduce its completion time by two days? (Enter a a numerical value without "$" or ",")

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books