Consider the following project. Use activity times as the most likely time for determining the critical path. Use the optimistic and pessimistic times (together with

Consider the following project. Use activity times as the most likely time for determining the critical path. Use the optimistic and pessimistic times (together with activity times) to determine expected completion time limits

  1. Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path (CPM) and CPM time.
  2. What is the expected time for 68, 95 and 99 percent Confidence Interval (CI) for the project?
  3. Show the 75%, Confidence Interval for the project (use section 7.4.3. page 225 for parts 2/3).
image text in transcribed
ID 7 Preceeding Start End Activity Staff Optimistic Pessimistic Activity Activity Node Node Time Required Time Time A S 1 3 4 2 6 B S 2 2 2 2 3 C S 3 4 6 2 4 D A. B 4 2 4 2 6 E B 2 5 3 2 2 4 F E 5 End 5 4 2 5 G C, E 3 End 6 5 2 6 H D 4 End 3 3 2 7

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cash Flows

Authors: Cyril Joseph

1st Edition

B0B84RHX2D, B0CPV8WDGT

More Books

Students also viewed these General Management questions