Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Consider the following project where times are in weeks. Activity Immediate Predecessors Duration A - 8 B - 12 C A,B 7 D B 4
Consider the following project where times are in weeks.
Activity | Immediate Predecessors | Duration |
A | - | 8 |
B | - | 12 |
C | A,B | 7 |
D | B | 4 |
E | A | 2 |
F | C | 3 |
G | E,F | 7 |
H | D,F | 3 |
What is the early finish for activity F?
a.
0
b.
22
c.
19
d.
3
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started