Consider the following project which starts on the 4 July. Calculate the Late Start date of the Design Screens task assuming there are no weekends.
Consider the following project which starts on the 4 July. Calculate the Late Start date of the Design Screens task assuming there are no weekends. That is, the developers work 7 days per week.
Task Name | Duration | Predecessors | |
---|---|---|---|
1 | Project started | 0 days | |
2 | Design screens | 7 days | 1 |
3 | Develop input screens | 5 days | 2 |
4 | Develop output screens | 4 days | 2 |
5 | Design database | 8 days | 1 |
6 | Develop database | 7 days | 5 |
7 | Project completed | 0 days | 3,4,6 |
Calculate the answer manually. It is possible to check your answer with Microsoft Project if you change the calendar so that developers work 7 days per week.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started