Question

1 Approved Answer

Consider the following project which starts on the 4 July. Calculate the Late Start date of the Design Screens task assuming there are no weekends.

Consider the following project which starts on the 4 July. Calculate the Late Start date of the Design Screens task assuming there are no weekends. That is, the developers work 7 days per week.

Task Name Duration Predecessors
1 Project started 0 days
2 Design screens 7 days 1
3 Develop input screens 5 days 2
4 Develop output screens 4 days 2
5 Design database 8 days 1
6 Develop database 7 days 5
7 Project completed 0 days 3,4,6

Calculate the answer manually. It is possible to check your answer with Microsoft Project if you change the calendar so that developers work 7 days per week.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Systems Today Managing In The Digital World

Authors: Joseph Valacich, Christoph Schneider

7th Edition

0133940500, 9780133940503

More Books

Students also viewed these General Management questions

Question

Explain and criticize the JamesLange theory of emotion.

Answered: 1 week ago