Question: Consider the following set of four processes. Their arrival time and time to require completing the execution are given in the following table. Consider all
Consider the following set of four processes. Their arrival time and time to require completing the execution are given in the following table. Consider all times in milliseconds. Implement the SJF algorithm on the given chart.
| Process | Arrival Time (T0) | Time required for completion (CPU Burst Time) |
| P0 | 0 | 10 |
| P1 | 1 | 6 |
| P2 | 3 | 2 |
| P3 | 5 | 4 |
Step by Step Solution
★★★★★
3.50 Rating (153 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Scheduling AlgorithmShortest Remaining Time First Preemptive Gantt chart ... View full answer