Consider the following table and find the Critical path for the project. begin{tabular}{|c|c|c|} hline Activity & Duration & Predecessors hline A & 3 &
Consider the following table and find the Critical path for the project.
\begin{tabular}{|c|c|c|} \hline Activity & Duration & Predecessors \\ \hline A & 3 & - \\ \hline B & 5 & A \\ \hline C & 7 & \\ \hline D & 3 & B, C \\ \hline E & 5 & B \\ \hline F & 4 & D \\ \hline G & 2 & C \\ \hline H & 5 & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|} \hline Activity & Duration & Predecessors \\ \hline A & 3 & - \\ \hline B & 5 & A \\ \hline C & 7 & \\ \hline D & 3 & B, C \\ \hline E & 5 & B \\ \hline F & 4 & D \\ \hline G & 2 & C \\ \hline H & 5 & \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started