Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days)

Consider the following table of activities A through G in which A is the start node and G is the stop node.

Activity Duration (days) Predecessor
A 10 --
B 20 A
C 5 A
D 3 B, C
E 20 B, C
F 4 B, C
G 10 D, E, F

On a piece of scratch paper, draw the network associated with this table and determine the following. Considering the lengths of all the paths, this project is _____ with maximum slack associated with any one activity of ____ days.

Multiple Choice

Insensitive, 17

Sensitive, 15

Insensitive, 15

Sensitive, 2

Insensitive, 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics An Intuitive Approach with Calculus

Authors: Thomas Nechyba

1st edition

538453257, 978-0538453257

Students also viewed these General Management questions