Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days)
Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days) Predecessor A 5 -- B 8 A C 7 A D 6 A E 9 B, C, D F 10 B, C, D G 5 E, F On a piece of scratch paper, draw the network associated with this table and determine the following. What is the critical path