Consider the following table of project information which can be used to create a network diagram. Which of the following is the TRUE statement? Activities

Consider the following table of project information which can be used to create a network diagram.
Which of the following is the TRUE statement?
Activities
Predecessors
Duration in Days
A
10
B
A
30
C
A
35
D
A
32
E
B, C, D
31
F
D
32
G
E, F
2
1.
The critical path is A, D, F, G
2.
The critical path is A, C, E, G
3.
The critical path is A, D, F, G
4.
The highest float in the network is 2 days
5.
The critical path is A, B, E, G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions